Summer Construction Begins on Nine Mile Road

The city hopes to avoid traffic issues with Thornton Creek Elementary before Northville schools begin on Sept. 4.

Construction began this week on Nine Mile Road from Beck Road to Taft Road and will last until September.

During construction, the road will remain open to one-way westbound traffic only; the eastbound lane will be closed.

According to Novi Director of Public Services/City Engineer Rob Hayes, the contractor hopes to have the road re-open to two-way traffic by Sept. 1, weather permitting.

Find out what's happening in Northvillewith free, real-time updates from Patch.

Hayes said the city hopes to avoid traffic issues with , which is located along this section of Nine Mile, before Northville schools begin on Sept. 4.

Detour signs have been put up, directing cars to 10 Mile or Eight Mile roads.

Find out what's happening in Northvillewith free, real-time updates from Patch.

The city is resurfacing the road as well as the following:

  • Drainage improvements
  • Pavement repairs
  • Removal or replacement of concrete curbs, gutters, sidewalks and ramps in some areas

The project is contracted out to AJAX Asphalt and is 80 percent federally funded.